Solar farms now viable without subsidy or tariffs

Posted on

Solafields is expecting to commence construction of two of its solar farms on a subsidy-free basis early in 2020.

Reduced solar module prices, reduced engineering costs and a reduced cost of finance have all enabled large scale solar to become viable, with no revenues other that the UK wholesale power price.

The economics are very tight and solar farm leases now need to be 50 years long to give enough time to recover the capital cost of the installation.

Lidsey Farm public exhibition Monday 14th January

Posted on

Solafields is proposing to build a solar farm of up to 10MW at Lidsey Farm, near the village of Shripney and in the parish of Aldingbourne, West Sussex, located on low-grade agriculture land approximately 1km east of Lidsey Road/A29, with direct access from the A259 relief road.

We would like to invite the local community to a pre- application public exhibition taking place:

Date: Monday 14 January 2019 Time: 4.00pm – 7.30pm
Location: Felpham Memorial Village Hall, 17-19 Vicarage Lane, PO22 7DZ

Members of the project team will be available to answer your questions and welcome feedback.

We look forward to seeing you at the exhibition and hearing your views.

Ingham North solar farm receives planning approval

Posted on

Solafields is delighted to announce that the Ingham North solar farm received planning permission from St Edmundsbury Borough Council, reference DC/16/2140/FUL, on 24th March 2017.

Bishop’s Waltham solar farm phase 1 commissioned

Posted on

Phase 1 of the Bishop’s Waltham solar farm was commissioned in February 2017. This phase was the construction of 5MW of the total 12MW consented for the site.

Ingham North solar farm public exhibition Wednesday 11th May 2016

Posted on

Our proposed solar farm north of Ingham would generate up to 13MW of electricity to feed directly into the local electrical grid network, generating enough renewable electricity to power up to 3,900 average UK homes.

The solar farm would save up to 6,000 tonnes of carbon dioxide per annum, or 180,000 tonnes over the proposed 30 year life of the project.

Site and Location
The site is approximately 51 acres/ 20 hectares of land north west of Ingham. The location proposed is well screened, over the brow of the hill, surrounded by existing mature hedges and trees and out of view from Ingham village.

This proposal replaces the previous application for a solar farm by Gamma Solar. The new location north of the original site comes following feedback on the Gamma Solar scheme from the local community.

InghamN OS location

The site location and access are outlined in red. The previous application area is shaded in light blue. The whole solar farm would lie within a single field of lower grade 3b agricultural land.

Consultation
A pre-application public exhibition, where members of the project team will be on hand to discuss the proposal and answer any questions, is being held:

• Date: Wednesday 11 May 2016
• Time: 3.30pm – 7.30pm
• Location: St Bartholomew’s Church, The Street, Ingham, Suffolk, IP31 1NH

Planning Process
Following on from the public consultation, the completion of the project team’s site analysis and the on-going pre-application discussion with St Edmundsbury Council officers, it is likely a planning application will be submitted later in the year.

Community Benefit
We operate a community benefit fund for all of our projects, which can sponsor a variety of local initiatives. We welcome suggestions for local projects to be considered; ideas include solar or heating projects in local buildings, educational projects and other projects that would benefit the community.

As well as financial benefit, the solar farm would provide ecological and environmental benefits. A nectar-rich grass and wildflower mix would be introduced on the site, which would be grazed by sheep and be a haven for birds, bees and other wildlife.

The project would pay significant business rates to the local authority and provide employment opportunities both during construction and in operation.

Local Suppliers
Should the project be granted planning permission, we would look to use local suppliers where possible.

The wide variety of businesses and individuals who may be able to work on the project include: electrical engineers, electrical supplies, maintenance, civil engineers, plant hire, security, local accommodation, site facilities, groundsmen, landscaping, nursery plants, solar panel cleaning, fencing contractors and haulage.

Bishop’s Waltham planning application submitted

Posted on

Following on from the public exhibition held in November 2014, we have recently submitted a planning application to Winchester District Council for a solar farm at land west of the B2177 Winchester Road between Bishop’s Waltham and Waltham Chase.

As a result of feedback received at the consultation, we have made substantial number of amendments to our original proposals:

• The size of the scheme has been reduced from 30 hectares down to 26 hectares

• Additional planting and increased hedge heights have been incorporated into the application to help further screen views and reduce visual impact.

• We have guaranteed we would not expand the solar farm into the fields to the west of the proposed site.

• Community ownership of the solar farm has been proposed, offering community investment opportunities that prioritise those living in Bishop’s Waltham and Shedfield parishes. Please see ‘Community Ownership’ section below.

Proposal
The planning application is for a 12MW solar farm, which would generate enough renewable electricity to power the equivalent of 3,636 average households . It would save around 5,160 tonnes of CO2 annually and make an important contribution to local and national renewable energy targets.

The visual impact of the proposed development is minimal. Existing trees and hedgerows provide good natural screening, with additional planting of new mixed native hedgerows being carried out where required.

Agricultural usage and biodiversity
The land would continue in agricultural use for the 30-year life of the solar farm, with seasonal sheep grazing around and underneath the panels, and a nectar-rich grass and wildflower mix would be introduced, which would be a haven for birds, bees and other wildlife.

An agricultural assessment shows the site is classified as predominantly lower-grade agricultural land (Grade 3b and 4) and thus it is considered appropriate for a proposal of this kind. At the end of the project’s life, all of the equipment will be removed and the land will be completely restored to agricultural use.

Design
Photovoltaic (PV) panels would be laid out in rows (arrays) running from east to west across the site. The panels would be angled at 20 degrees, 2.3m high and 0.9m at their lowest point with approximately 5m spacing between rows, allowing for biodiversity enhancements and sheep grazing around and beneath them.

A surrounding deer fence is necessary to protect the solar farm from damage, and to prevent any large mammals from injuring themselves on the equipment. The local deer would still have access to many neighbouring fields. The fence would include a ‘small animal’ gate to allow continued foraging and nesting within the site, during the lifetime of the solar farm. Security systems would use infra-red sensors and the solar farm would not be illuminated at night.

Noise
The only components of the solar farm which make any noise are the inverter / transformer stations, which are located towards the centre of the layout and emit low levels of noise which would not be audible from outside the site boundaries

Access
Access from the B2177/ Winchester Road is currently available in the north-eastern and south-eastern corners of the site. Both access points comprise dropped kerbs and hard standing off the highway and are currently used by agricultural vehicles.

The main access for construction vehicles would be via the southern access. The northern access would provide the access for the substation building.

Sufficient visibility currently exists in both directions for the southern access. Should the northern access be needed for construction vehicles, it is proposed to limit construction traffic movements to left in and left out manoeuvres only.

Construction
Solafields would implement best practice during construction to minimise any nuisance to the local community. The construction period for the solar farm is anticipated to last approximately 20 weeks. During this period approximately 304 HGVs would visit the site for materials and equipment deliveries. This is an average of 15 HGVs per week.

Maintenance
During operation, vehicle movements associated with monitoring, maintenance and cleaning are very low. Cleaning is usually less than annual and would depend on local air quality conditions. Typically 10-20 visits per year would be scheduled for a solar farm of this size, usually made using a small van.

Land Management & Decommissioning
A specialist land management team would be employed to maintain the site throughout the operation of the solar farm. The team would be responsible for implementing the ecological enhancements outlined above.

At the end of the solar farm’s life all hardware will be dismantled, removed and recycled. All existing hedgerows and trees would be retained throughout the life of the project, and the decommissioning process would see the reinstatement of the existing field shapes and sizes intact and, as a result, the landscape would not suffer any permanent alteration.

Community Benefit Fund
We operate a community benefit fund that can sponsor a variety of local initiatives, such as solar or heating projects in local buildings, educational projects and other projects which would benefit the community. A number of suggestions were given for the proposed Community Benefit Fund at the public exhibition in November 2014, the most popular being improvements to existing rights of way and support for Priory Meadow. Should planning permission be granted and the project proceeds to construction, we would invite local community organisations to apply for grants from the fund for local projects.

Community Ownership
We want the local community to have the opportunity to invest in the proposed solar farm and share in its success. To achieve this aim we are partnering with Hampshire Renewable Energy Co-operative (HREC) which is a non-profit making organisation set to promote community ownership of renewable energy projects.

We have agreed with HREC that, should planning permission be granted and the project proceed to construction, we would accept up to 10% of local community investment in the proposed solar farm. HREC have agreed to co-ordinate that investment on behalf of local people and would undertake all the legal work and issue a prospectus detailing the terms of the investment opportunity. The investment would be offered once the solar farm is commissioned and producing electricity, which could be as early as spring 2016.

Depending on the size of the final development we would expect there to be an opportunity to invest between £500,000 and £1,000,000 in return for a prorated share of the income from the scheme. We would want to encourage as many investors as possible and HREC suggests that typical investments should be between £1,000 and £10,000.

Initially the opportunity to invest would be restricted to residents of Bishop’s Waltham and Shedfield, giving you priority to invest in the scheme. If you are interested please register your interest on the HREC website – www.hampshire-energy.co.uk – and we will communicate with you further nearer the time of the proposed offering, which we would anticipate will be in early 2016.

Ongoing consultation
The planning application – which includes the associated studies and reports – will be available on the Council’s website once they have validated the application. You will be able to provide your feedback directly to Winchester District Council as part of the Council’s consultation process.

Castle Combe and Horam solar farms both make the March deadline

Posted on

Solafields’ projects at Castle Combe (16MW) and Horam (8MW) both successfully commissioned on time to make the deadline for the last Renewables Obligation projects before the market fully moves to the new Contracts for Differences. The construction teams from vogt and Dragon Infrastructure both did an amazing job getting complex construction and lengthy cable routes completed in very tight timescales. We are also extremely grateful to the local residents for their patience during the road works for the cable route.

Baker’s Farm commissioned

Posted on

Our 12MW solar farm at Baker’s Farm, Sidlesham, successfully commissioned in mid-March, well ahead of the month end deadline. Landscaping works are now being completed and the awards for the commmunity benefit fund will shortly be notified.

New solar farm proposed near Bishop’s Waltham

Posted on

Proposal
The proposed solar farm would generate up to 15MW of electricity to feed directly into the local electrical grid network, generating enough renewable electricity to power around 4,545 average households.

The solar farm would save up to 6,700 tonnes of carbon dioxide per annum.

Site and Location
The proposed site is approximately 20 hectares/ 50 acres in size and is located on land west of Winchester Road, north of the Clewers Hill junction, approximately 1km south of Bishop’s Waltham and 1km north of Waltham Chase.

Consultation
A pre-application public exhibition was held on Thursday 20 November 2014 at the Jubilee Hall, Bishop’s Waltham. The leaflet summarising the key details of the project is available at the following link:

Bishops Waltham solar farm info leaflet

UK’s largest solar farm commissioned

Posted on

On 12th September 2014 the 37.8 MWp Crundale Solar Farm in Pembrokeshire began to generate renewable energy. Construction of the project was completed in only eight weeks. The project is a joint development between ib vogt GmbH and Solafields Ltd. and is currently the largest operating solar farm in the UK.

The 37.8 MWp solar farm at Crundale was connected to the grid on 12th September 2014 as scheduled. It has 147,672 modules producing over 38 GWh of renewable electricity per annum, enough to power more than 11,000 UK homes and save 20,000 tonnes of carbon dioxide (CO2) emissions per annum. The solar farm project has been purchased by institutional investors. It was jointly developed by Solafields and ib vogt GmbH, with vogt solar Ltd also acting as EPC.

Solafields and vogt are jointly developing a portfolio of over 100MWp in the UK.